Working on a new utility-scale solar project, a developer chooses a transformer that meets the project's technical requirements, offers a competitive price, and can be delivered on schedule.
But months later, the picture changes. New trade rules increase the cost of imported equipment. The supplier can't provide the documentation needed to support a domestic content claim. Replacing the transformer means updating engineering studies, securing new approvals from the utility, and requalifying parts of the interconnection package. As construction timelines compress, the project risks missing its commercial operation date.
Procurement isn't as simple as it used to be; today's equipment decisions don't just depend on cost and technical performance. A single procurement choice can carry implications for trade policy, domestic content requirements, supplier documentation capability, interconnection specifications, construction schedule, and financing assumptions. These risks stack on top of one another, and a change in one area can ripple across the entire project.
The developers that consistently protect their project economics identify these overlapping risks early on, and allocate them before they become costly delays.
Procurement has become a stack of constraints
Not long ago, selecting major equipment was a matter of balancing three main variables: cost, technical performance, and lead time. Developers compared suppliers, evaluated specifications, negotiated pricing, and chose the component that best fit their engineering and commercial requirements. They still need to do all this, but now have additional layers of complexity to deal with on top of the basics.
This complexity stems from recent changes in trade policy, incentives under the Inflation Reduction Act, increased supply chain scrutiny, and ongoing equipment shortages. For example, a recent market report from PwC found high capacity transformer lead times are currently stretching out to as long as four years. Demand for generator step-up transformers has grown 274% since 2019, while substation power transformer demand is up 116%. And recent extensions of tariff exclusions for solar manufacturing equipment show how quickly trade conditions can shift. US median module prices rose to $0.28 per watt in Q1 2026, up from $0.25 a year earlier, as trade duties and domestic content rules reset the market.
Instead of optimizing for a single objective, procurement teams are now balancing competing priorities, and every sourcing decision has consequences that stretch beyond the procurement team itself. For example, the lowest-cost supplier might have higher exposure to tariffs or import restrictions. The fastest delivery schedule could complicate domestic content compliance. Even basic questions like where a component was manufactured can have significant downstream implications.
This collection of overlapping requirements is the procurement risk stack: the multiple layers of technical, commercial, regulatory, and contractual risk attached to a single equipment decision. The layers, in sequence, are: trade policy; domestic content requirements; supplier documentation capability; interconnection specifications; construction schedule; and financing assumptions.
Each layer constrains the one below it. A tariff change forces a supplier substitution, which changes the equipment specification, which triggers an interconnection restudy, which slips the COD, which moves the tax year for the ITC claim, which changes the financing terms. No single layer caused the problem; the structure did.
These patterns show up across the projects on our platform. In a recent look at flagged risks spanning over 80 projects across 20 states, the same layers recur: transformer procurement and documentation gaps, generator step-up lead times running 14 to 18 months, long-lead HV equipment, interconnection milestones colliding with COD targets, and unresolved ITC safe-harbor and domestic content questions, with FEOC exposure cutting across many of them.
The first casualty: schedule
Schedule sits near the bottom of the stack, but it's the first place project teams feel the impact — precisely because it's the layer that absorbs every disruption the layers above it couldn't resolve. If a developer needs to replace a transformer or inverter halfway through a project, the solution isn't always as simple as ordering a new one. The original equipment may not be available anymore, or no longer make economic sense.
Alternative inverter models may have different electrical characteristics, requiring updated power-flow or protection studies before the utility will approve the revised design. Similarly, substituting a transformer with different impedance or ratings may require portions of the interconnection package to be revisited. One-third of 2024 interconnection withdrawals came at the facility study or agreement phase, late enough to disrupt neighboring projects and trigger cascading restudies. Procurement teams also have to evaluate new suppliers, negotiate contracts, and confirm manufacturing timelines.
Project timelines are built under the assumption that each decision will hold. When a sourcing decision changes, the project isn't just dealing with one new problem — it's dealing with several previously-resolved problems that are now open again simultaneously, each with its own
stakeholder, timeline, and cost.
The risk is also asymmetric. A procurement change in month 4 of a 36-month project is manageable. The same change in month 28, when studies are finalized, lenders are in due diligence, and the EPC contractor is sequencing deliveries, can be unrecoverable without significant cost. Transformer lead times make this worse. With major equipment now taking two years or more from order to delivery, developers have to lock in specifications in the first weeks of development, often before interconnection studies are done and before the site is fully controlled. They are committing to equipment they can't change by the time they know enough to know if it's right.
Domestic content isn’t just where equipment comes from
The Inflation Reduction Act's domestic content bonus changed what procurement teams need to focus on when it comes to equipment sourcing. The regulation encourages developers to buy U.S.-made products, but it also raised the bar for verification and documentation, often in ways that don't surface until tax equity due diligence months later.
To determine whether a project qualifies for the domestic content bonus, developers may need to look beyond where a component was assembled, digging into where key materials and subcomponents came from, whether suppliers can provide sufficient documentation, and how those claims will hold up during financing and tax due diligence. The thresholds for meeting these requirements have risen over time and vary by when a project starts construction. Lenders and tax equity investors often require documentation supporting domestic content claims before relying on those assumptions in project financing.
This documentation could include a bill of materials tracing each major component back to its manufacturing origin; country-of-origin certifications from suppliers; and in some cases, manufactured cost breakdowns that separate domestic from imported value-add. Some lenders require third-party verification; others require supplier representations and warranties baked into procurement contracts. All of them will haircut the domestic content premium out of their underwriting if the documentation package has gaps.
This shifts procurement from a transactional exercise to one that depends on traceability. A supplier may offer a competitive product with strong technical performance, but if it can't provide the documentation needed to support a domestic content claim, the project's financial assumptions may no longer hold. Documentation capability thus needs to be evaluated at the same stage as technical specifications and pricing, not as an afterthought.
Risk doesn't disappear; It moves
Even the best procurement strategy can’t eliminate risk entirely. There will always be elements outside developers’ control, like evolving trade policies or supplier manufacturing delays. The next shift is already visible: a Section 232 investigation treating polysilicon as a national security commodity could add upwards of 15 cents per watt to imported modules, enough to make some import lanes uneconomical. This is why contract structure is as important as equipment selection.
Well-structured contracts don't prevent procurement disruptions, but they do establish a framework for responding to them. When responsibilities for tariff changes, supplier substitutions, redesign costs, or schedule impacts are defined in advance, project teams can move quickly instead of renegotiating commercial terms in the middle of construction. In that sense, the difference between projects that hold their budgets and schedules and those that don't often comes down to how procurement risk was allocated before problems emerged, not after.
Procurement agreements increasingly need to address questions like: who’s responsible if tariffs go up after a purchase order is signed? What happens if a supplier can no longer support a domestic content claim? Who absorbs the cost of redesign if a component becomes unavailable? The provisions that matter most are increasingly standard in well-negotiated procurement agreements, and they shape a project's financial and schedule risk long before any equipment arrives on site. Procurement has become as much about negotiating risk as negotiating price.
Procurement as cross-functional discipline
As procurement decisions have become more complex, the groups responsible for making them have expanded as well. Though procurement or supply chain teams head up major equipment selection, there are more cooks in the kitchen now than there used to be. Engineering may approve a technically equivalent substitute while finance evaluates its impact on tax assumptions, legal reviews whether existing contracts accommodate the change, and project managers consider schedule implications.
Though each group has a different priority, they’re all trying to keep the project on track. To do so effectively, they have to coordinate their decisions. When teams evaluate sourcing decisions in isolation, risks that look manageable within one function can create unintended consequences for another.
Engineering can approve a transformer substitution as technically equivalent without knowing it will trigger an interconnection restudy that kills the COD. Finance can confirm a component meets the domestic content threshold without knowing the supplier can't produce documentation in the form tax equity requires. The failure here isn't any single bad decision; it's that no one is accountable for how the decisions interact.
The best-performing projects hold working sessions early in procurement planning to address cross-functional questions before equipment is specified. Which parameters are embedded in the interconnection studies, and what is the tolerance on each before triggering a restudy? Which domestic content claims are baked into the tax equity underwriting, and what does the lender actually need to see from suppliers? Which contracts have tariff and substitution exposure, and how is it allocated? These questions can only be answered with engineering, finance, legal, and project management all in the same room.
As the procurement risk stack continues to grow, success will depend on making sourcing decisions with a thorough understanding of how they'll affect the rest of the project. In today's market, procurement is about managing the interconnected risks that determine whether a project ultimately delivers on its commercial goals.
Enjoying this deep dive?
Stay up to date on market insights for teams who build, buy, and finance renewable projects.